Calculators

FlowGantt | Interactive Gantt Chart Manager for Project Planning

FlowGantt - Advanced Gantt Chart Manager

FlowGantt

Advanced Gantt Chart Manager

How to Use โ–ผ

  • Start with a pre-built example project or create your own tasks
  • Add tasks with name, duration, category, and priority level
  • Edit tasks: click the "Edit" button in the task list or double-click a task bar on the chart
  • Set dependencies between tasks (hover over help icons for explanations)
  • Toggle between Hours, Days, or Weeks time scale
  • Use zoom controls: +/- buttons, slider, or mouse wheel to zoom in/out
  • Navigate the chart: click and drag to pan, or use scroll wheel to zoom at cursor
  • Mobile: pinch to zoom, swipe with one finger to pan the chart
  • Critical path is automatically calculated and highlighted in red
  • View slack/float time to see scheduling flexibility for each task
  • Drag tasks on the chart to reschedule them (removes dependencies)
  • Check the minimap for full project overview
  • Explore the glossary to learn project management terms
  • Generate reports to analyze your project schedule
  • Export your Gantt chart as PNG for documentation
100%

๐Ÿ“ Project Overview

๐Ÿ“– Project Management Glossary โ–ผ

Critical Path
Think of it as your project's backboneโ€”the sequence of must-complete tasks that sets your absolute fastest completion time. Miss a deadline here, and your whole project timeline shifts.
Slack/Float
Your breathing room. It's how much you can delay a task before it starts affecting when your project wraps up. Tasks on the critical path? They have zero wiggle room.
Dependency (FS, SS, FF, SF)
Relationships between tasks. FS (Finish-to-Start): most common, task B starts after A finishes. SS (Start-to-Start): both start together. FF (Finish-to-Finish): both finish together. SF (Start-to-Finish): rare, task B finishes when A starts.
Gantt Chart
A visual project management tool showing tasks as horizontal bars along a timeline, illustrating start dates, durations, and dependencies.
Milestone
A significant point or event in the project, typically with zero duration, marking the completion of a major phase or deliverable.
Early Start/Finish
The earliest possible time a task can start or finish based on predecessor dependencies.
Late Start/Finish
The latest time a task can start or finish without delaying the project completion.

๐Ÿงฎ Critical Path Formulas โ–ผ

Early Start (ES)
ES = Max(Predecessors' Early Finish)
Early Finish (EF)
EF = ES + Duration
Late Finish (LF)
LF = Min(Successors' Late Start)
Late Start (LS)
LS = LF - Duration
Total Float/Slack
Float = LS - ES = LF - EF
Critical Path Condition
If Float = 0, then task is on Critical Path

๐Ÿ“Š Project Analysis Report โ–ผ

Click "Generate Report" to analyze your project

Tasks & Dependencies

Design
Development
Testing
Planning
Documentation
Deployment
Critical Path
No tasks yet. Load an example project or add your first task!

๐Ÿ“š Load Example Project

Choose a pre-built project to see FlowGantt in action:

๐Ÿ’ป Software Development
Complete software project lifecycle from planning to deployment
๐Ÿ—๏ธ Construction Project
Building construction phases with dependencies
๐ŸŽ‰ Event Planning
Conference organization from concept to execution

โœ๏ธ Edit Task

ยฉ 2026 EngiSphere.com